The delivery terms that matter most when importing an 18–150 kW natural gas CHP system are the agreed delivery point, the transfer of transit risk, the allocation of freight and destination charges, and the conditions for accepting the equipment. A competitive equipment price can become an expensive purchase if the buyer discovers that unloading, customs clearance, storage, or commissioning support sits outside the quoted scope.
For buyers comparing an 18-150kW natural gas CHP exporter, a useful starting point is to request quotations against the same named destination and scope. FCA can suit procurement teams that control their own freight. DAP can simplify transport coordination when the buyer can manage import clearance and unloading. Neither choice, by itself, establishes when the CHP will be ready to operate. That requires separate contractual milestones.
Specify the delivery point precisely enough to price the remaining journey.
An Incoterms® 2020 rule should appear with a named place or port. “FCA China” or “DAP customer site” leaves too much room for disagreement. State the factory address, freight terminal, or project address, and identify the receiving point where necessary. A truck arriving at the site gate may still be some distance from the plant room or equipment foundation.
The choice of rule should follow the buyer’s logistics capability and the project’s receiving arrangements:
EXW may look attractive because it exposes a low factory price, but it places loading and export arrangements largely on the buyer. An overseas buyer may find export formalities difficult to manage. Compare it with FCA at the factory before assuming it offers a saving.
FOB and CIF are intended for sea or inland waterway transport, with delivery and risk transfer tied to loading aboard the vessel. For containerized equipment handed to a carrier before vessel loading, FCA, CPT, or CIP may better match the physical handover. Under CIF, the seller pays freight and arranges insurance to the destination port, while transit risk transfers at shipment. A destination in the quotation does not necessarily mean arrival risk remains with the seller.
Compare the cost of reaching the installation position.
Ask each bidder to identify included and excluded charges. The comparison should cover export packing, origin handling, main freight, insurance, destination terminal charges, customs brokerage, duties and taxes, inland haulage, unloading, and movement into the installation position. Treat commissioning and installation as separate lines unless the contract expressly includes them.
Destination charges deserve particular attention under CPT, CIP, and port-based quotations. Establish which handling charges are included in the seller’s carriage contract and which will be collected locally. Otherwise, two apparently comparable freight quotations may leave different balances payable after arrival.
For an 18–150 kW CHP package, rated electrical output does not establish shipping size. An enclosure, heat recovery equipment, exhaust components, control panels, or separately packed accessories can change the number and dimensions of packages. Obtain a preliminary packing list during quotation and a final list before dispatch, showing gross weight, dimensions, lifting points, and any transport restrictions.
A supplier’s larger equipment also illustrates why freight assumptions must remain model-specific. AMICO’s 1800kW natural gas generator set, model AMC1800NS, has stated transport dimensions of 13,000 × 3,000 × 4,000 mm and a weight of 26,000 kg, both subject to the actual configuration. Those figures cannot serve as a logistics basis for an 18–150 kW CHP purchase. Request packing data for the exact package being ordered.
Check the final delivery route before booking transport. Vehicle access, overhead clearance, ground conditions, and crane positioning can determine whether delivery to the site is straightforward or requires additional handling. Allocate storage, container detention, demurrage, and redelivery costs according to the cause of delay, including late documents, delayed clearance, or an unavailable receiving area.
Make packaging, documents, and insurance contractual deliverables.
A general promise of “export packing” gives the buyer little basis for assessing protection. Specify packing suitable for the transport route and expected storage period: moisture protection, corrosion prevention, restraint of movable components, protection of electrical cabinets, and clear handling marks. Require a packing method that allows safe lifting without loading vulnerable piping or enclosure panels.
The packing list should account for loose CHP components, including heat recovery connections, sensors, exhaust accessories, and installation hardware where supplied. Missing small parts can prevent commissioning even when the main engine-generator package arrives undamaged. Agree how discrepancies will be reported and how replacement parts will be delivered.
Set a document schedule before shipment. It should cover the commercial invoice, packing list, transport document, origin documentation where required, insurance evidence where applicable, and technical or conformity documents needed for the destination and installation. Align document descriptions with the actual equipment. Customs classification and import requirements should be reviewed with the buyer’s broker before dispatch.
Where the buyer carries transit risk, arrange insurance from the contractual risk-transfer point. Where the seller provides insurance, review its coverage rather than relying on the word “insured.” Examine exclusions, deductibles, the insured party’s claim rights, and whether unloading, inland transport, and temporary storage fall within the policy. CIF and CIP carry different default insurance requirements under Incoterms® 2020; neither removes the need to assess coverage against the route.
Separate dispatch, arrival, and operational acceptance.
“Delivery within twelve weeks” is ambiguous unless the contract defines the event and its starting conditions. Distinguish factory readiness, dispatch, arrival at the named destination, and commissioning completion. Specify whether the schedule begins after the deposit, approved drawings, agreed gas specifications, or another documented condition.
Incoterms allocate delivery obligations, costs, and risk; they do not establish CHP performance acceptance, payment terms, ownership transfer, or warranty commencement. Put these matters in the purchase contract. Factory testing should have an agreed scope and release criteria. Site acceptance should address the contracted electrical and useful heat output under defined gas, ambient, and operating conditions.
Commissioning also depends on site readiness. Assign responsibility for gas supply and pressure, electrical connections, ventilation, exhaust routing, and the heat recovery circuit. Define whether the supplier provides remote assistance or an attending engineer, who pays travel costs, and what happens if the site is unavailable on the agreed date. Establish warranty timing explicitly so that delayed installation does not silently consume the expected operating coverage.
Before placing the order, procurement should be able to trace responsibility through every handover: factory to carrier, carrier to destination, vehicle to foundation, and installed equipment to accepted operation. Any gap should become a priced scope item or an explicit buyer responsibility. The quotation is ready for comparison when the remaining cost and work are visible.